What's Being Built at the Village at Avon, and When Each Piece Opens

A new road and sidewalk curve beside golden November grasses beneath a sage-covered Colorado mountain hillside.

"The easy thing would have been to close this deal years ago, plop them down in the northwest corner of the property, and deal with planning later," Marcus Lindholm told the Vail Daily in July, after Traer Creek and Jasmine Development closed the deal that brings a Whole Foods Market to east Avon.

That choice explains what you see when you drive past Walmart and Home Depot this month. Planning came first, and building is following in a set order. Roads went in first, then the buildings that rely on them. The grocery store everyone talks about comes near the end. For anyone who lives in Avon or nearby in EagleVail, the changes to daily routines arrive years before the storefronts do.

The Order the Pieces Are Arriving

Every date below comes from the Town of Avon, the developers or the Vail Daily. Each one is an announced plan or target, so treat the timing as the schedule the builders set.

Piece What it is Timing as announced
East Beaver Creek Boulevard Realigned main road through the work area Town notice scheduled the opening to traffic for Oct. 28, 2026
Chapel Alley About 175 feet between Chapel Place and East Beaver Creek Boulevard Closure for approximately one month, scheduled from Oct. 28
Lettuce Patch Early Learning Center Child care for ages six weeks to five years Construction completed Sept. 10, 2026
Bosk Apartments 242 rental units at the east end Slated to open at the end of 2026
Whole Foods Market About 28,500 square feet Summer 2028
Skjól 122 condominiums Phase I fall 2028, Phase II spring 2029
The Promenade 50,000 square feet of mixed commercial, retail and residential space Being marketed, no tenants named

The first four rows affect how people drive and how families find child care. Whole Foods and Skjól have broken ground, and the Promenade is still at the marketing stage.

The Road Came First

The public work is the biggest piece so far, even though it gets the least attention. The Vail Daily reported in April that grading was finished across the valley floor, including the future Whole Foods site. The paper put the infrastructure package at about $25 million. That covers permanent improvements to East Beaver Creek Boulevard and Chapel Place, plus an extension of Crescent Hill Road east to the Bosk site.

The road has changed more than once. In late September 2025, the Vail Daily reported that a temporary road connected to East Beaver Creek Boulevard was about to be paved through the property. A Town of Avon notice dated Oct. 23, 2026 set Oct. 28 as the day a new temporary detour and the newly built East Beaver Creek Boulevard would open. The old detour was to be removed and traffic moved onto the new layout. The same notice closed about 175 feet of Chapel Alley, between Chapel Place and East Beaver Creek Boulevard, for approximately one month. By that estimate, the alley would reopen around the end of November. For updates, the Town's notice lists the Avon Engineering Department at (970) 748-4080.

That is a lot of road for an area where most of the new buildings don't exist yet. The Town and the Village at Avon metro district designed the roadway and stormwater systems together during a master-planning process that began in 2021 with the Los Angeles firm Jerde Partnership. Michael Lindholm of Traer Creek described the work in the Vail Daily as taking "more than four and a half years to work through the Jerde master plan with all of the different consultants, including working with the Town on master planning design and its impact on the Town's road layouts, stormwater, etc."

Then the Buildings That Depend on It

The first building finished in this round of construction serves families, not shoppers. On Sept. 10, 2026, the Vail Valley Foundation cut the ribbon on the Lettuce Patch Early Learning Center. It is an all-electric, 13,595-square-foot building with 12 classrooms and four outdoor playgrounds. It can eventually serve up to 165 children, and about 55 percent of its licensed capacity is set aside for infants and toddlers. Access Early Education Foundation runs the center Monday through Friday from 7:30 a.m. to 5:30 p.m., year-round. The Foundation set a target start date of Oct. 12, and families can join a waitlist for future openings through Lettuce Patch.

The site is the result of an older commitment. Under the Village master plan, Traer Creek had to give the parcel, Planning Area E, to the Town for educational use. VVF President and CEO Mike Imhof noted at the ribbon cutting that it had been "an empty lot just over a year ago."

Down the newly extended Crescent Hill Road, the 242-unit Bosk Apartments are, according to Traer Creek's April release, slated to open at the end of 2026. Bosk joins two complexes already standing in the Village, the 240-unit Piedmont and the 244-unit Buffalo Ridge. Traer Creek counts 807 housing units and 368,573 square feet of commercial space built or under construction across the Village to date.

The Bus Stops Were Planned Before the Storefronts

The sequencing shows up in transit too. When Avon staff walked the Town Council through the west-end plans in September 2025, the Vail Daily reported that "bus stops have already been established within the transportation layout." The same plan calls for a multi-use recreation path from Chapel Square across the valley floor to Piedmont and Bosk.

Avon's mobility schedule runs from Mar. 31 through Nov. 25, 2026. It lists Chapel Square/Mountain Family Health, Piedmont eastbound and westbound, and Walmart as stops. The Blue Line serves Walmart, Home Depot and Traer Creek Plaza. The Red Line covers those same three stops plus Buffalo Ridge. Both run daily every 30 minutes until 10 p.m. The current schedule ends the week after Thanksgiving, so the Town's bus page is the place to check the next one.

The Store Comes Last

The Vail Daily reported in July that Whole Foods is expected to open in summer 2028. That puts it two ski seasons away. In September 2025, Kensington Development Partners told the Vail Daily that the projected opening was fall 2027 and added, "Subject to change." According to the Vail Daily, Whole Foods first approached Traer Creek in 2020 and agreed to add underground structured parking as part of the site planning.

Mile High CRE reported on Oct. 6, 2026 that Phase I had broken ground on the 40-acre west-end parcel. Kensington is leading it in a joint venture with Jasmine Development Group, an affiliate of the longtime landowner, and FDC Development. Phase I includes the grocery, 7,500 to 12,500 square feet of additional retail, and Skjól. Skjól is a Scandinavian-inspired building with 122 condominiums, private spa facilities and direct trail access. The same report put Skjól's contracted pre-sales at more than $100 million.

What Sits Beyond Phase I

East of Phase I, Kensington has started marketing the Promenade, a six-acre district planned for 50,000 square feet of commercial, retail and residential space. The developer is targeting lifestyle, wellness, food and beverage, and outdoor recreation brands, along with local businesses. No tenants have been named.

When Avon staff presented the plans in September 2025, the Vail Daily reported that the longer-term concept went further. It included a two-acre lake, public park space, and more apartments, condominiums, hotels and retail. The development agreement designates 0.6 acres for a lake, so the larger version would need council approval. Town Manager Eric Heil called that area "probably phase III."

All of it falls under the Village at Avon planned unit development. The PUD covers more than 1,700 acres, running from just east of Chapel Square to Planning Area I behind EagleVail across the Eagle River. It allows up to 2,400 homes and 825,000 square feet of commercial space outside Planning Area I. On April 14, 2026, after five reviews, the Avon Town Council approved the latest set of amendments 6-1. The Town and Traer Creek had filed them jointly, and they requested no increase in density. According to the Vail Daily, the process began when the Town asked about using a parcel near the child care center for community housing. Michael Lindholm said he hopes the Town can partner with Habitat for Humanity there.

The Village was annexed into Avon in 1998, and public infrastructure work started in 2002. Most of the roads, stops and child care for the next phase are already in place or scheduled to open, and the Whole Foods is set for summer 2028.

Over the coming seasons, east Avon will change how people drive through it, how they reach the Blue and Red Lines, and where new homes and shops go. At Ron Byrne & Associates, we follow Village at Avon milestones as they happen and can explain what each phase means for property across the Mid Valley. Schedule a Private Consultation whenever you'd like a closer look at how the new east end fits your plans.